Description
Muskegon Construction Company worked with the owner and architect as a team to deliver innovative solutions to the project’s needs. Accurate and timely cost information and strictly controlled scheduling techniques contributed to the success of the project.
Features:
• Security and technology systems added and upgraded to provide state-of-the-art monitoring and fully integrated access control for the entire facility
• Additional state funding permitted an additional 1,200 square feet of mezzanine space inside the newly constructed jail.
• Mezzanine construction was integrated with minor impact on the original project budget and schedule.
Summary
- Size:
- 21,900 SF
- Type:
- Municipal
- Budget:
- $4,100,000
- Date Completed:
- 10/01/1999