Farmers Insurance Campus Expansion
Caledonia MI View Map Project Phase: Under Construction Budget: $40 M
Descriptions
Wolverine Building Group
A new three-story 275,000 square foot office building set to become the new call center. The new construction of a second building includes a 100,000 square foot print and distribution center.
D9 Systems, Inc.
D9 Systems will be providing labor and materials for steel stud framing, insulation, drywall and acoustical ceilings.
Kent Companies, Inc.
This 275,000 square foot foundation package was installed right through the heart of a cold, snowy, Michigan winter. Careful coordination was required with the excavator to dig only the footing pads and strip footings that could be poured the same day. Blanketing and temporary heat was applied and monitored to insure proper curing of freshly poured concrete.
Over 700 lineal feet of concrete wall, up to 35 feet tall, was required for various below grade areas. There were also some architectural finished concrete retaining walls near the main entrance which required a two-sided form liner.
All of this work was completed within the project timeline due to the experience of Kent Companies’ employees.